This fall, Builders Paving is scheduled to resurface the stretch of Old Sutton Road between Dundee Road and County Line Road. The Village of Barrington Hills posted the Cook County schedule on October 23. Milling is planned for the week of November 2 and the new asphalt surface for the week of November 9. Permanent pavement markings, reflectors and culvert cleaning are set for the week of November 16, weather permitting. The village's notice says plainly that this is a Cook County project on a county-maintained road. Questions go to the county's project representative, not to Village Hall.
The village gets a notice there and has no control. A few hundred feet off that same road, a pending case concerns a parcel just past the Barrington Hills village line.
A Parcel Just Past the Line
On the east side of Old Sutton Road, south of Penny Road and north of Route 72, sits a parcel of about 4.4 to 4.5 acres. The two figures come from different pages of the same application. The address is 15N803 Old Sutton Road. The land is unincorporated, just south of the Barrington Hills boundary, and it borders Forest Preserves of Cook County land on two sides.
The county application is dated June 4, 2026. It asks the Cook County Zoning Board of Appeals for two approvals under case numbers SU-26-0002 and VA-26-0017. The ZBA's September 23 agenda summarizes them:
- The special use. A "unique-use" special use to operate "a commercial truck parking business for 50 dump trucks."
- The variance. Permission to raise the height limit for an accessory structure from 15 feet to 20 feet 2 inches. The structure is a 3,000-square-foot garage that the application says is for the owners' personal vehicles and fewer than five trucks.
The parcel is zoned R-1 Single-Family Residence District under the Cook County ordinance. Inside the village, the R-1 district is the one that defines Barrington Hills. Village Code Section 5-5-4-1 sets its minimum lot area at 5 acres for a single-family detached home. The two districts share a name, but different governments write them, and different bodies decide what gets an exception.
A Letter That Argues the Facts
Village President Brian Cecola signed a letter dated September 14. It asks the ZBA to recommend denial of both petitions and cites no statute or court decision. Instead, it argues about the ground. It says Old Sutton Road is narrow and unlit, has no shoulders, and isn't wide enough for two dump trucks to pass each other safely. It also notes that residents, bicyclists, equestrians and forest preserve visitors use the road. The letter points out that the property is less than 1,000 feet from Spring Creek, and that the surrounding area runs entirely on private wells and septic systems with no public sewer to handle stormwater. The road it describes is the same one Cook County has scheduled for resurfacing this fall.
The village's letter also draws on recent history along the road. It states that a property less than 200 feet to the north had been used for truck parking until Cook County enforcement ended it. The village presents that episode as evidence of how the use fits with the area.
The village posted its comment publicly on September 15. Neighbors filed too. The objection packet the county posted summarizes 22 letters. The concerns it tallies include traffic and safety in 17, zoning compatibility and precedent in 15, noise and rural character in 14, environmental issues in 11, and closeness to sensitive areas in 10.
The application also contains a land-use report dated October 13, 2022, which describes a different plan: six company trucks plus 44 truck spaces for rent. The request in front of the ZBA in 2026 is the one on the agenda, for up to 50 dump trucks.
Where the Case Stands
The ZBA's September 23 minutes record that testimony was taken on SU-26-0002 and VA-26-0017. They then list Unfinished Business and adjournment, with no decision on the petition. The ZBA's October 7 agenda doesn't list the case and names November 4 as the next meeting.
The Barrington Hills Observer, a local news and commentary site, reported on October 25 that a recording of the September 28 Village Board meeting pointed to a postponement until at least January 2027. According to the Observer, the reason is that the application and objections had not been sufficiently available for public review before the September hearing. The Observer also reported that it was unclear whether new objections would be admitted. The ZBA hasn't posted a continued hearing date.
County Records
The records are public, and Cook County explains where to find them. ZBA hearing dates, agendas and approved minutes are on the county's Legistar portal. Minutes go up after they're approved at the following meeting. Applications and objection letters for pending cases, including the Old Sutton file, are on the county's supplemental information page.
All of this is general information, not legal advice. If a zoning question could affect a purchase, an attorney who handles land use can confirm how the rules apply to that specific parcel.
For more on Barrington Hills, Connie Antoniou is here. Let's Connect.